January 9. 2006

Jan Flatten
c/o Forest Supervisor James Boynton, Okanogan Valley Office
1240 Second Avenue South
Okanogan, WA 98840

comments-pacificnorthwest-okanogan-tonasket@fs.fed.us

Re: Comments regarding the preliminary Environmental Assessment for the Buckhorn Mountain Access Road and Related Activities Project (EA)

I hope that you will carefully consider these comments. We do not want to live with the repercussions of poor decision making.

OHA takes the public trust responsibility the USDA Forest Service (FS) administers very seriously. We expect you to use the best information available as the basis for your decisions. Unfortunately the current EA fails to include relevant information and therefore calls into question the value of the document as a decision making tool. The public has the right to know what the impacts would be before an action is approved or undertaken.

The EA does not provide an objective examination of the connect between the proposed mine and the activities proposed on National Forest System (NFS) lands. The proposed pipe line and the water coming out of the pipe cannot be separate from the water going into the pipe. Where the water is coming from and why cannot be isolated from the environmental impacts to NFS land. The actions that the FS is responsible for and the subject of this EA are integral parts of a large-scale development project which would have significant and cumulative environmental impacts for which an environmental impact statement (EIS) is required. Incorporating the Draft Supplemental EIS (DSEIS) does not release the FS from its responsibility to apply its measure and fully review the significant environmental impacts by doing an EIS under NEPA.

In this document, the FS attempts to extricate itself from the process and produce a minor review of a small piece of a larger project and fails to address the purpose of an environmental assessment which is to determine whether a proposal will have significant environmental impacts. The road access and other related facilities are integral parts of a larger project. The amended Plan of Operations for which this preliminary Environmental Assessment is written is the “proposed Buckhorn Mountain Project on lands administered by the Forest Service” not the access road and related activities project as the title of this document suggests. When the EA uses the phrase “project activities” it should clarify whether it relates to the mine or the road and infiltration area or other activity on National Forest System (NFS) land.

Please consider and explain how this project and the Methow Transmission Project administratively differ and why that project is currently undergoing NEPA/SEPA review. In both instances new and reconstructed access is needed through federal land and a special use permit would be required. Both projects would have significant environmental impacts. Why is the FS as co-lead agency producing in an EIS for one and only doing an EA in the other? The FS should join with Ecology and prepare a comprehensive document that reviews the significant impacts of this proposal in an EIS under NEPA/SEPA.

The EA and available supporting documents fail to acknowledge, fail to mitigate, and/or downplay the long-term significance to the environment and quality of life. This includes impacts to ground and surface water (quantity and quality), downstream water users, residents and tourists (health and safety, air quality, noise, transportation and scenic beauty), and fish and wildlife and their habitat. The EA fails to address the deficiencies that the PCHB rejected including water rights and water rights mitigation, hydrologic and geochemical modeling. The EA fails to consider minimizing Marias Creek road impacts by reducing its width from 24 foot to 12 foot. Most of these issues were brought up in scoping comments. For these and the reasons below the EA is inadequate. The FS should make a determination that the impacts of this project including the direct, indirect and cumulative impacts are significant and merit an Environmental Impact Statement.

The following comments explain why the EA in its current form does not adequately address potential direct, indirect and cumulative impacts that would be caused by developments on NFS land for the proposed mine on Buckhorn Mountain. The EA does not look at alternatives that would minimize the impacts nor does it offer sufficient mitigation to make the impact acceptable. It would appear that the document was prepared to conclude that the impacts of the proposal are not significant, rather than as an objective examination of the data or an objective projection of the potential impacts. Much of the information is misleading because it extrapolates data inappropriately and draws conclusions from inadequate information or fails to draw conclusions or mitigate situations when the information would warrant action. There is not a sufficient basis for the responsible officials to come to an objective decision.

The EA uses the word “preliminary” in the document title but does not explain what it means. Is EA is not a draft document? When would the EA be considered final?

The EA fails to include a list of references that the FS relied on to make the document. Without a list of references, the document is not accountable to published models and methods that inform decision-making. Further, with no list of references the document is unsubstantiated. This shows little respect, consideration, or appreciation for other agency and the public’s involvement in the review effort especially considering that the document was released on December 9 for a 30 day comment period right through the holiday season.

SPECIFIC COMMENTS

Chapter 1
Background
(page 1) The EA states that “due to a subsequent State of Washington decision to rescind a key permit for the project….”. In actuality the State did not rescind a permit, a quasi-judicial board granted the appeals of the State’s decisions and ordered water rights and water quality certification reversed and vacated respectively. This should be corrected because this point is important in explaining the conclusions of law that the mine project must adhere to. As a reminder we include the The Pollution Control Hearings Board (PCHB) January 19, 2000 decision, finding of facts, conclusion of law, and order in it's entirety (appendix # 1), as part of our comments so that it may be entered into the record. Each and every technical issue, and conclusion should be addressed in the EA. A full accounting of the issues, documents and predictive modeling rejected by the PCHB (see appendix 1) should be included so the public can be assured that inappropriate information is not being relied on in the EA.

The sub-section goes on to state that the “the decision space was narrowed to only those activities…”. The narrower decision the FS has to make does not in any way excuse the FS from reviewing all the impacts of the project that relies on FS land for it’s implementation.

Management Direction (page 4) While ‘the Forest Plan has a forest wide standard and guideline that requires mining claimants be given reasonable access to their mining claims’, the project that the road access and related facilities supply is located on private land and not subject to this standard and guideline. The project should instead be managed under multiple use guidelines that balance and considers all of the goods and services that the federal public land provides
.
Purpose and Need (page 4) Part of the purpose and of an environmental assessment is to determine if a project would have significant environmental impacts. If the answer is yes, an environmental impact statement (EIS) is required. The State of Washington in the DSEIS for the mine proposal, that the FS has incorporated into this EA, has already established that it would have significant environmental impacts. The FS must make a determine as to whether the impacts of this project including the direct, indirect and cumulative impacts are significant.

Proposed Action (page 6) According to the EA, the Forest Supervisor proposes to approve access to the proposed mine along with other related activities without a determination of whether the impacts would be significant. Further the Forest Supervisor is proposing to approve access and related facilities to a project that the Pollution Control Hearings Board (PCHB) has determined as a “conclusion of law” does not meet requirements of law. Unless and until there is some reason to believe that the established law has been somehow changed, the Forest Supervisor has a responsibility to consider and respect them as the law of the land.

In its Conclusions of Law at #59 the PCHB stated;
“The focus of our environmental laws must be on preventing pollution and habitat degradation. It is not legally sufficient to proceed with the proposed mine without much more specific knowledge of the potential impacts from the development and meaningful means of preventing and protecting against adverse consequences of the development. The long-term engineered solutions proposed in this case are legally insufficient.” (Emphasis added)

It appears that the FS has come to a predetermined result (ie. no significant impact). The FS must ensure the scientific integrity of all studies. Despite the fact that the mine as proposed would be a private land development, it would be a direct impact of the FS approval here.

The EA should include a list of which of the underlying documents in the 1997 FEIS are still being relied on as accurate and which the PCHB has rejected in its technical issue and/or conclusion of law and are no longer reliable or relevant. Much of the information in the Crown Jewel Project EIS is almost a decade old and out of date.

A big part of the proposed action is access roads. The limited maps lack road labels making it extremely difficult to follow explanations in the EA . The large scale of nearly identical maps make it difficult to identify locations referenced in the document.

Decision Framework (page 6) Once again the document fails to identify the responsibility to make a determination whether the direct and indirect impacts along with the cumulative impacts would be significant to people and the environment. There is no way for the Forest Supervisor to determine if the mine proposal that the road access and related activities and facilities would or could obtain water rights, or comply with the waste discharge and other environmental protection laws. The Washington Department of Fish and Wildlife (DFW) has stated in its comments to the DSEIS for the Buckhorn Mine proposal, “it does not appear that adequate mitigation measures will be in place to offset impacts such as the permanent reduction in stream flow in Myers Creek and the long-term reduction in all the headwater tributaries originating on Buckhorn Mountain.” Therefore there is no way the Forest Supervisor can legitimately make a Determination or Mitigated Determination of No Significance.

Public Involvement and Consultation, Consultation (page 7) There is no mention in this section of consultation with the Washington State Department of Ecology or the Washington State Department of Fish and Wildlife. The Forest Service relationship with Ecology and Fish & Wildlife should be clearly explained in this document. The document should list who at the various agencies has been consulted on this project.

Public Involvement and Consultation, Issues (page 7) The EA fails to discuss or consider the unavoidable adverse direct, indirect, and cumulative impacts so that alternatives to minimize or mitigation developed and undesirable and unintended consequences can be avoided. A direct impact of the FS' approval would be the private land development of the proposed mine. This issue should be fully discussed in the EA.
Issue # 1; Measured by should include miles of fence on all lands not just NFS administered lands.
Issue # 3; Measured by should include not only the amount hauled over NFS lands but the quantity spread on NFS and other lands and include an analysis of the quantity of impacts.
Issue # 7; The description of the issue should include that the site that is proposed for obtaining gravel for upgrading and constructing the Marias Creek access road is known to be badly infested with noxious weeds. Alternatives to deal with this and additional mitigation should be developed to prevent or at least minimize the spread of weeds so that herbicide spreading on public land can be minimized.
Issue #8; Not only would the proposed action have cumulative impacts with the mine, there would be direct and indirect impacts as well. A direct or at least an indirect impact of water coming out of the pipe and into the infiltration area is the water going into the pipe. The impacts of where the water is coming from should be considered in the EA. The direct, indirect and cumulative impacts of the project with the mine should also be measured by; the quantity and quality of stream habitat that would be reduced in winter. The decrease in stream flow in consecutive low precipitation years and under drought conditions. The functional loss of the reduction in seeps, springs, ponds, and wetlands should be qualified. The reduction in fish and fish habitat. The Impact of increase chloride in Marias Creek.

Chapter 2,
Alternatives, Management Mitigation, and Monitoring
(page 15) It appears that the FS has come to a predetermined result (ie. no significant impact). The FS must ensure the scientific integrity of all studies. Despite the fact that the mine as proposed would be a private land development, it would be a direct impact of the FS' approval here. (See Decision Framework above)

Alternatives Considered but Eliminated From Detailed Study (page 15) Although this section acknowledges that all the alternatives in the 1997 FEIS considers different proposals for on-site processing of ore, for some reason, they are incorporated by reference in this EA. Since the Forest Service incorporates the 1997 FEIS in this EA, OHA incorporates the entire administrative record of that EIS in our comments to this preliminary EA. They are available at the Tonasket Ranger District.

Components Considered but Eliminated From Detailed Study, Ore and Supply Transportation Operating Schedule, Operating Season (page 18) states, “The Forest Service would only shut down when haul is causing environmental damage.” What standards and benchmarks are being used to assess this environmental damage? It states that cost would be borne by the mining company. How would the cost of increased sedimentation be assesses and compensated?

Alternatives Fully Developed
Infiltration Areas and Supply Pipeline
(page 26) States, “An infiltration area for treated mine water meeting State and Federal Water Quality Standards would be constructed….” There is no justification for this statement in the EA. In their December 28 comment letter to Ecology regarding the Buckhorn Mtn proposal the EPA stated, “In addition, the predicted effluent quality from the proposed mine water treatment system would not meet surface water quality criteria for some parameters.” The FS must show how it arrived at and can justify its conclusion.

Alternative B – Proposed Action (page 26) States that this alternative is based on the Amended Plan submitted March 15, 2005 and ‘subsequent clarification of this plan’. The EA should state specifically what documents it received that provide clarification of this plan.

Ore Haul Route (page 26) The maps fails to label roads making it difficult to follow the text explanation of the alternative
.
Supply Haul Route (page 27) What mechanism insures that suppliers will use the routes that are described in the EA? Are they legally bound in some way or are they free to use the easier route of Beaver Canyon to the Chesaw side of the Pontiac Ridge Road?

Water Monitoring (page 29) The EA states that there are presently 8 monitoring wells and a number of water monitoring stations on National Forest System (NFS) land. The location and purpose of these water monitoring devices should be identified.

Water quality is basic to the significance of the impacts of the proposed infiltration area and road access. The EPA has stated, in its December 28 comment letter to Ecology, “We do, however, have some significant concerns with the DSEIS. In particular, the predictions of water quality conditions during and post-mining may be underestimated…” The FS cannot ignore its responsibility under NEPA to use all the information available prior to making statements and certainly decisions.

What criteria was used to determine that 4 or more water monitoring devices described in the EA would be adequate? What evidence is there to insure that NFS land would be protected from pollution.

Management and Mitigation (page 52) Issuing of permits and approvals does little or nothing to ensure enforcement of management and mitigation. Specific ongoing enforcement with trigger criteria should be identified especially since some of the impacts from project components may not be completed until after the “60 or more years” needed for the mine to reach equilibrium and that environmental consequences are predicted based on successful implementation of these measures.

Water Discharges, Water quality (page 57) The DSEIS does not predict water quality standards would be met. See comment above. In addition, water quality predictions are not conservative.

Water Discharges, Flow Augmentation (page 57) This item recognizes the direct and indirect impacts that would be caused by the proposed underground mine on NFS land. These direct and indirect impacts should be expressed throughout the document and the mine components (surge pond, treatment plant, etc) should be fully described and explained in this document. The monitoring described in this section is not reflected in the water monitoring component in the Alternative section above.

Land Use (page 58) Seven items in this section related to range management. They are poorly explained and some these items may have impacts of their own that should be analyzed. The EA should have a section that relates specifically to range management.

Land Use, Noxious Weed Control (page 61) The $4,000 fee the proponents would pay for weed control would do little to stop the spread of noxious weeds if the current plan is implemented. The Beal gravel pit is known to be infested with noxious weeds. This is where the spread of weeds should be managed not after the fact. It would be better to minimize the spread of weeds than to have to remediate an infestation.

Monitoring Measures (page 76) This section is insufficient to protect the environment. A complete monitoring plan should be required with the EA. This section uses words like ‘some’ and ‘portions of’ to refer to what monitoring would take place. The EA should be clear about what monitoring would take place, when, and by who. What other agencies are referred to that would have permit requirements and require monitoring? What specific monitoring and compliance would the FS require? The EA should include a table of all monitoring that is proposed, who would be responsible, when would monitoring be done and what would trigger remedial action.

Water Resources Monitoring (page 77) The description in this section of water quality, quantity, and levels of regulated substances monitoring are completely inadequate to assess the impacts that would occur and especially if the goal is to prevent, reduce, or mitigate the impacts. The timing of monitoring water flows along haul road are especially inadequate, monthly is not adequate and quarterly in the winter leaves no room for informed action.

What specific surface monitoring stations would be set up for streams, seeps, and springs impacted by ore haul, water infiltration, and mining operations? What ‘baseline monitoring network’ is referred to that ‘would be preserved to the extent possible’? What baseline water quality and quantity parameters would be used to assess if remedial action is needed?

Groundwater monitoring wells should be located where they could best assess impacts not necessarily as close a s possible. What ‘baseline monitoring network’ is referred to that ‘would be preserved to the extent possible’? What baseline water quality and quantity parameters would be used to assess if remedial action is needed?

This section indicates that post closure monitoring would continue at least 3 to 5 years and the focus would be long term water quality. Three to five years would not be considered ‘long-term’ especially for a project that is predicted to take 25 to 60 years or more to reach hydrologic equilibrium.

Fish Populations (page 78) Every other year for monitoring fish populations as presented in this section of the EA is completely inadequate considering the impacts of this proposal. By the time changes in fish populations were discovered by biennial monitoring as proposed in the EA and attributed to project activities it would be too late to develop and implement adequate mitigation or project modifications. Do “project activities” in this section relate to the mine or the road and infiltration area?

Noxious Weed Monitoring (page 78) It should be noted that the gravel pit that is proposed to supply gravel for the Marias Creek Access road is infested with noxious weeds. Some type of monitoring to insure these weeds do not spread would be important to minimize the problem.Chapter 3.
Environmental Consequences (page 89) This section summarizes and cites specialist’s reports. There should also be a list or table of references of both the citations in the EA and of reports that were relied on in the specialist’s reports.

The FS incorporating Ecology’s DSEIS does not release the FS from its responsibility to review the direct, indirect and cumulative impacts by doing an EIS under NEPA. The road access and related facilities are integral parts of a larger project.

Hydrology(page 111) A definition and scope of this section should be explained.
Ecology’s DSEIS is a draft document with numerous problems, it should not be relied on as a basis for the FS analysis of impacts to NFS land.

Existing Condition, Climate (page 111) Impacts to the hydrology in this area are of primary importance. The lack of confidence in the underlying data was one of the main causes for water rights and water quality certification to be vacated and revoked respectively. The accuracy of the climate information is questionable. The mean temperature cites Pentec Environmental 2004. When Pentec Environmental 2004is reviewed it cites Forest Service and Ecology 1997 and actually a correlation from Republic and Molson and not from within the project area. This information was subsequently readjusted before the PCHB hearing. The FS should be using the most up-to-date information and not present a chain of different citations. Further the figures for precipitation do not have a citation. Accurate precipitation information is critical since stream flows are modeled from this information. The information in Pentec 2004 states, “ The average annual precipitation for the area ranges from 15 inches in Republic to 12 inches at Omak in the west precipitation at Conconully, northwest of Republic, is approximately 15 inches. Over the region, precipitation averages approximately 21 inches annually (PNRBC, 1970).” Conconully is not northwest of Republic but northwest of Omak and 21 inches does not come close to the numbers being averaged.

Wetlands (page 113) This section does little to describe the existing condition of wetlands within the project area. Mentioning the various consultants that have mapped wetlands and the various amounts each one has come up with for various agencies and the mining proponent does not provide any representation of the quantity or quality of the wetlands in the project area. This section should describe not only the quantity or quality of the wetlands but their structure and function as well.

The EA should include information about the changes that have occurred over the years regarding the water flowing out of the Roosevelt adit.

Soil Permeability (page 113) The description of the existing condition of soil permeability for the infiltration gallery is inadequate. This issue is extremely important because it would receive the direct impacts of the dewatering of the mine yielding impacts from water quality and quantity. Any casual observer would note the large road cut adjacent to the proposed infiltration area. It is likely that the outwash sand and gravel overlaying the till and/or glacio-lacustrine sediments are from this road cut. This should be discussed in the text.

The text fails to describe that water currently flows from beneath the proposed infiltration area. Water discharged to this area would likely flow directly into surface water. This should be realistically analyzed and reflected in the documentation.

Water quality (page 114) There is a disconnect between the FS EA and the Ecology DSEIS. While the EA states that any water discharged must meet water quality standards, the DSEIS predicted treated effluent concentrations shown in Table 3.7-1 exceed groundwater criteria for chromium (as stated), and are equal to the criterion values for nitrate and selenium and also equal to the MCL for antimony. When compared to surface water criteria and aquatic life criteria, treated effluent concentrations exceed surface water criteria for chromium (by 70 times), lead (by 2 times), mercury (by 33 times), ammonia (by 8.6 times), selenium (by 2 times), silver (by 3 times), and zinc (by 1.1 times). The impact of the release of treated effluent is not discussed in the EA.
(See Addendum #3; Memorandum by Ann Maest PhD; Buka Environmental Re: Comments on Projected Operational and Post-Closure Water Quality for the Buckhorn Mountain Project, December 14, 2005. Attached and incorporated.)

Water Infiltration Gallery Effects for all Action Alternatives
(page 118) This section seems to limit water discharge into the infiltration area to 40 gpm with the rest going into “the Roosevelt adit or wetland in Marias Creek.” This misleads the reader into believing that the rest of the water would go down Marias Creek. This is not the case since currently the discharge from the Roosevelt adit is routed back into Nicholson Creek. See page 3-39 of the 1997 FEIS; “At this time, surface and subsurface flows in Nicholson Creek includes most of the Roosevelt adit flows.” The water rights application for the mine requests 100 gpm for dewatering mine shafts. The impacts of discharging this water into Nicholson Creek should be fully and realistically examined in the EA.

Effects of Salts for Dust Suppressants for all Action Alternatives
(page 119) This section acknowledges that magnesium chloride has not been found effective, in some cases, even with product reapplication, for periods of more than about one year, and that it should only be used for short-term (less than one year) stabilization. Yet the EA ignores its own recommendation to limit the use of magnesium chloride and only when water quality testing shows a problem would action to stop its use be taken. This blatant disregard for aquatic degradation, pollution prevention, and anti-degradation laws is unacceptable.

Alternative B and B1, Direct and Indirect Effects (page 121) This section fails to consider increased sediments due to the infiltration gallery will increase sediments in Nicholson Creek and that the increase would increase as dewatering increased. The gallery is proposed in soils that are highly permeable over soils that have low permeability. There is already a steady flow from the base of this area near the road cut. The addition of 40 gpm would go right through the gravel outwash into surface water producing sedimentation into Nicholson Creek. (see comment above from page 118)

The EA should describe in detail what the impacts of the estimated reduction on average of 124 gpm to the baseflow of Toroda Creek would be (as per the bottom of page 123 of the EA). See comment Amphibians (page 131) below.

Cumulative Effects (page 129) Incorporating the state’s DSEIS does not release the FS from its responsibility to apply its measure and fully review the cumulative environmental impacts under NEPA
The EA continues to build on the foundation that the PCHB rejected. In Its Conclusions of Law at #61 the PCHB stated, “….As thoroughly as this proposed mine has been studied and evaluated, it is not at all certain that we have a clear understanding of the hydrogeology on the site. There are substantial questions about the stream flows, groundwater flows and relative precipitation…” Yet the EA continues to rely on much of the same data.

The EA should describe where the proponent would get all the water discharged onto NFS land. This should include all water that would be dewatered in order to mine or water used for dust suppression. Water rights have been a pivotal issue to the mine in the past and since they have been rejected in the past because it was not clear that issuing them was lawful, the EA should show what has change to assume that water is available for this project. While water rights are not generally the subject to an EA, in this case because of the PCHB decision and that adverse impacts to senior water rights are the significant impact identified by the DSEIS, it is altogether fitting and proper that water rights should be reviewed as part of this EA.

The EA should clearly indicate the total water discharge that would flow from the proposed pipe line and exactly how that water would be distributed. Where would that water go, what would the quality of that water be, and what would the impacts of that discharge be. It should be noted that the water right application is for 100 gpm. for mine dewatering, industrial and mitigation with the impacts clearly defined. The EA should clearly state the specific rate at which groundwater would be pumped out of Buckhorn mountain including yearly and project totals. The DSEIS (page 3.7-26) uses a minimum recharge value of 1.9 inches/year but the corresponding figure on page 2-3 of the FEFLOW model is 1 inch/year.

It would seem that the FS failed to coordinate the EA with the state’s review of the same environment. Each agency has a different description of the affected environment and the estimated quantity of water in the seeps, springs and streams that may be temporarily or permanently altered. The EA should explain how the changes would impact the function of the seeps spring and headwater streams including but not limited to moderation of temperatures, riparian vegetation, sediment transport, and storage release attenuation.
The million-gallon surge pond seems to be a catch all for mine water that could be used for almost anything. What is the legal status of this proposed reservoir? The mitigation of streams on the eastern side of Buckhorn during critical times of the year should be comprehensively discussed in the EA. The piecemeal approach to mitigation is unacceptable.

The EA fails to encompass the estimated “25 to more than 60 or more years” that it would take for the water level of the mountain to reach equilibrium after mining. All aspects of the EA should recalibrated to this time frame.

The EA cannot ignore the impacts that the discharge into the infiltration gallery would have on the west side of Buckhorn Mountain. The EA must contain an accurate water balance. The EA must, but fails to, answer the basic questions; where does the water come from and where does it go to.
Drought conditions should also be considered but are not.

The EA cannot ignore the procedures for mine closure and post-closure monitoring since they directly impact uses of NFS land. The proposed plan for addressing groundwater impacted by contact with the mined area apparently relies upon extracting the impacted groundwater by pumping, circulating the impacted groundwater through the treatment system, and infiltrating the treated groundwater into the mined area (DSEIS, section 3.7.2.2). However, the intent of the proposed plan is unclear. For example, it is reasonable to expect that this approach would require maintaining groundwater levels equivalent to the lowest elevations achieved during dewatering to prevent release of impacted groundwater from the mine workings to the surrounding aquifer (if groundwater levels were allowed to rise, then capture of all impacted groundwater could not be assured). However, the proposed plan does not appear to consider the concept that maintaining depressed
groundwater levels within the mined area may be necessary. For example, the plan apparently assumes that all extracted and treated groundwater will be discharged to the infiltration gallery (DSEIS, section 3.7.2.2), but previously noted in the same section that “the infiltration gallery may not have sufficient capacity to infiltrate all of the water”. In addition, maintaining low groundwater levels within the mined area is inconsistent with the stated goal of allowing groundwater levels within the workings to recover swiftly in order to minimize impacts to groundwater quality anticipated from acid generation within the vadose zone and impacts to surface water and groundwater quantities anticipated from mine dewatering. It is also unclear whether the proposed approach will actually decrease impacts to applicable standards within a reasonable timeframe. The proposed approach does not explicitly commit the operator to prevent the release of impacted groundwater from the former mine workings, define the conditions under which the operator would transition to discharging treated mine water back into the mined area, or describe how such discharge would be effected (i.e. whether an infiltration system would be constructed).
See Appendix # 4, Udaloy Environmental Services to Okanogan Highlands Alliance December 2005, (Udaloy 2005) attached and incorporated.

Water Quality; The EA should also not ignore the ground water quality impacts of the mine for it could directly impact NFS land. The plan is to allow surface to runoff from development rock and ore stockpiles to mix with groundwater and then monitor the groundwater downstream and if needed enhance water capture and treatment. Development rock and ore stockpiles could be covered so that groundwater would not be further contaminated thereby reducing the pollution that would eventually surface on NFS land. All potentially acid-producing rock could and should be mixed with cement to further reduce the inevitable acid mine drainage.

Water quality in the Southwest Zone is predicted to be poor and outside the groundwater capture zone yet no modeling of the potential seepage to downgradient groundwater and surface water during operations was conducted. The DSEIS states that groundwater monitoring would be conducted to confirm that groundwater from this zone is being captured yet of the four monitor wells proposed none are close to the southwest zone. These impacts would take place on NFS land and should be included in the EA.

The DSEIS predicts that discharge to the infiltration gallery would not to exceed water quality criteria, four constituents are at or above water quality standards. The impacts of the release of treated effluent to surface water is not adequately considered in the EA. An evaluation of the consequences of releasing treated effluent to the Nicholson and Marias Creek watersheds, both in terms of quantity and quality of surface and groundwater, should be addressed in the EA.

The DSEIS predicts that water treatment will most likely be needed for nitrates and ammonia as the mine refills with water (25 or more than 60 or more years) and that the treatment facility would remain operational beyond that. This period should be considered part of the mine operation or at least the reclamation and be included in the EA when defining the project life. The EA should reflect that water treatment may be required for more than 60 years after actual mining stops; in other words, reclamation far exceeds the amount expressed throughout the document.

The approach to arriving at the best and worst case water quality values for operational and post-closure water quality in the DSEIS is very convoluted and represents several iterations that are poorly presented in the geochemical appendix.

Surface Water, Water Quantity;
(see above) The DSEIS states that effluent from the treatment facility would be required to meet water quality standards yet concentrations shown in Table 3.7-1 show four constituents at or above water quality standards going into the infiltration gallery. The impacts of the release of treated effluent to surface water is not adequately considered in the EA. An evaluation of the consequences of releasing treated effluent to the Nicholson and Marias Creek watersheds, both in terms of quantity and quality of surface and groundwater, should be addressed in the EA.

Surface Water, Water Quality; The EA should discuss the impacts that could occur from increased water flows going down Nicholson Creek. What would the impacts be of stopping that flow after 7.5 years. The area of the proposed infiltration gallery already has surface water flows coming from under the glacial till that was apparently excavated from the cut bank where near MW-3. The significant discharge into this area will likely result in creation of a direct path into surface water that would likely cause significant erosion down Nicholson Creek.

For discharges of development rock and ore stockpiles see above. In addition contaminated water from development rock and ore stockpiles that infiltrates into groundwater via well or other infiltration should be considered a point source of pollution and required an NPDES permit.

Marias Creek Haul Route; Alternative road designs should be looked at that would meet project criteria for road access while minimizing impacts to public resources.
The bottom of page 123 refering to dust-control water for the Marias Creek haul route states that baseflows of Toroda Creek would be reduced on average by about 124 gpm but fails to explain what the impacts of this would be. Instead the section concludes that no senior water rights have been identified in fall and winter so it does not represent an impact in fall or winter from a water rights perspective. The EA should clearly express the impacts of the reduced baseflow on Toroda Creek and affirm that the creek has been closed to new appropriation since the 1950’s and that the change in use would constitute an expanded use and would most likely be denied.

The EA should evaluate the impacts of extracting groundwater from the Toroda Creek basin during early mine development.

Aquatics (page 129) Aquatics should be defined. A general description should include a mention of seeps and springs and their function as wetlands. In fact it is important to include the functions of wetland in the environment not simply how to identify them. Some of the functions that should include are moderation of temperatures, riparian vegetation, sediment transport, and storage release attenuation. The EA should consider the wetland edges of headwater streams and acknowledging that they accumulate to represent a notable resource. These wetland edges of headwater streams are not considered in this EA but should be.

Existing Condition, Amphibians (page 131) It is good that the information that the EA contains a mention that Toroda creek has been closed to surface water availability based on fisheries dating back to the 1950’s but this information should be at least under fisheries or hydrology, not amphibians. In addition it should be mentioned that this was on the recommendation of Washington State Department of Fish and Wildlife.

Marias Creek, Wetlands, Seeps, and Springs (page 133) The description of the wetlands is inadequate for the public to understand the locations and impacts of the proposed action. The EA approximates 8 acres of wetland but fails to provide any way of assessing there location or relationship to the proposed activities. Are they above or below the road? There are also numerous wetlands near and downstream from the proposed infiltration site that should be included

Nicholson Creek, Wetlands, Seeps, and Springs (page 133) The description of the wetlands is inadequate for the public to understand the locations and impacts of the proposed action. The EA approximates 9 acres of wetland but fails to provide any way of assessing there location or relationship to the proposed activities. Are they above or below the road? The headwater of Nicholson Creek that is commonly referred to as the Gold Bowl should be recognized in the EA as a wetland even though much of its vegetation has been degraded by grazing and drought. Likewise, there are numerous wetlands downstream from the proposed infiltration site. One directly below and others portions of the 9 acre wetland (RA1 through RA7) drain down Nicholson Creek
.
Environmental Consequences, Effects Common to All Action Alternatives, Water Infiltration System, Direct/Indirect Effects (page 134) The EA should consider whether changes in water quality and quantity Water from the infiltration system could impact the full range of aquatic habitat and organisms.

Water from the infiltration system would reach surface water relatively quickly. Predicted effluent water quality exceeds a number of surface water criteria and/or aquatic life criterion values. The impacts of the discharge of this effluent on downgradient aquatic habitat and life should be evaluated for the EA. The discharge could also cause increased turbidity that should be considered. The EA should consider that water from the treatment facility could be of higher temperature and would cause additional impacts. Will the headwaters of Nicholson ‘blow-out’ from too much water? How would Nicholson Creek headwaters be impacted?

The DSEIS states that “the water quality would be assured because the treatment system would treat it as needed.” The DSEIS goes on to say, “as a contingency measure, the amount and location of delivery of water could be adjusted, based on monitoring.”

Which wetlands created by the seeps and springs on NFS land are above the drawdown in the water table are expected to have reduced flows or go dry from the water discharged into the infiltration gallery? At what elevation would the broadest part of the cone of depression intersect the slope of the mountain? The EA should describe how long each of the impacts of the mine, such as dewatering are predicted to last, and what the basis is for that prediction. What flows reduction from water going into the infiltration gallery should be expected from the Roosevelt Adit. Without a clear plan of how, by who, when and to what specific quantity flows would be augmented there is no way to understand what the impacts to wetlands would be or if mitigation would be effective.

Cumulative Impacts (page 134) The impacts of “shifting the water from one watershed to another” should be quantified. What would the improvements be to fish and other aquatic organisms in Toroda Creek and its tributaries and what would be the impact of reducing the water available on fish and aquatic organisms and habitat in the Myers Creek basin and its tributaries.

The EA should contain a complete water balance. How much water is expected to be released and where? What are the expected water losses to wetlands, seeps, and springs that augmentation is expected to offset during dry months.

The EA should be clear that the cumulative impacts of the water infiltration system when looked at with the impacts from the mine and specifically the dewatering of the mountain and water quality concerns would be significant. The EA needs to fully quantify the aquatic impacts in the other drainages on Buckhorn Mountain and recognize that the proposed action does not come close to mitigating the impacts thereby necessitating that they be considered significant, any addition to these significant impacts would be considered cumulative.
Other Direct/Indirect Effects Common to All Action Alternatives, (page 135) The failure of the EA to recognize that there are significant unmitigated wetland and aquatic Resources impacts are major flaws in the document.

Page 3.10-19 of the DSEIS states, A decrease in flow during the winter months has the potential to affect resident brook trout by exposing spawning gravels and reducing intragravel flow during the egg incubation period. There is no indication that this impact would be mitigated. It should be included in this section.

The EA makes the case that sedimentation is bad for fish and that sediments during at least the first three years could be expected. Prevention in subsequent years is dependent on vegetation growth. If monitoring indicates a problem then shrubs or trees would be planted. This is an inadequate solution. It takes years for trees and shrubs to grow and in the meantime fish are being harmed or dying. In addition it is recognized that elevated levels of salts and chlorides could be impacting fish and amphibian. If fish or amphibian mortality is detected, lignin sulfonate could be used which is another waste product with few relevant guidelines are available for minimizing environmental risk (see bottom of page 161).

The aquatic impacts to Marias and Nicholson Creek from reduced flows from dewatering and refilling of the Buckhorn Mountain aquifer should be included in the EA. If, how, and when those impacts would be mitigated should also be made clear.

The EA should include information about the changes that have occurred over the years regarding the water flowing out of the Roosevelt adit.

Alternative B and B1: Marias Creek Haul Route (page 137) The EA should quantify how much of the creek is adjacent to the road and not wide enough to intercept and hold sediments. The EA states that additional sediment in Marias creek could result in the loss of fish populations and that modeling indicates a 34% increase in sediments but that mitigation would reduce this. The EA should make some attempt to rate the effectiveness of this mitigation. Considering that the impact of additional sediments could be the loss of fish populations, there should be a high likelihood of success. The EA has different solutions in different places. In this section rocks, shrubs and/or trees would be planted along the silt fence and page 66 states that if sedimentation occurs activities causing it would be suspended or modified. Both are unrealistic considering the length of time and addition sedimentation planting would cause and transportation of ore is integral to the project. Additional mitigation could include excluding cows from the creek altogether.

How much of the approximately 8 acres of wetland that would be excavated for widening the road or the new road cuts. What is the likelihood that the wetlands would reestablish and occupy about the same area? How much of the wetland function would be reduced or lost? The reductions include flood water detention and retention, which allows peak flood flows to be reduced, groundwater recharge and discharge and water quality improvements. These impact should be quantified and considered in developing mitigation. How would the accumulation of salts and dust suppressant impact the health and function of the wetlands? How long would it take for the wetlands to recover? What is the likelihood of success? How would noxious weed introduction from the Beal pit impact recovering wetlands? What wetland function would be impacted by culvert placement?

Of the 160 feet of wetland that would be filled no mention is made of mitigating the impacts. How would the Forest Service ban on fill that contains noxious weed seed be enforced?

Cumulative Effects for All Action Alternatives (page 142) It does not seem that any real attempt was made to look at the cumulative impacts of this proposal on aquatic resources. This section is totally inadequate. The EA should consider present, and foreseeable future grazing impacts as well as foreseeable future mining impacts especially considering the almost 200 mining claims Crown controls in the area.
Drought conditions should also be considered.

The cumulative impacts of the Forest Service changing the course of water flowing from the Roosevelt mine adit into Marias Creek so it would flow into Nicholson Creek for the previous mining proposal should be considered. If this is controversial, the history of changes to the flow of said waters should be discussed in the EA. In addition, the EA should discuss the possibility that the cumulative impacts of past mining exploration has created preferential flow paths and change the hydrology of the area.

Ongoing Activities (page 143) Grazing should be considered in this section
.
Reasonably Foreseeable Future Action (page 145) The assertion that there are no cumulative impacts from surface water baseflows that are expected to would decrease in Marias and Nicholson Creeks effecting the viability of the fry and egg survival because road construction has no impact on baseflows is absurd. The infiltration gallery is an integral part and directly linked to dewatering of the mine and together formulate the cumulative impacts. The same goes for the Toroda Creek and Upper Myers Creek watersheds.

Biological Evaluation (page 145) This should be adjusted to reflect these comments.

Other issues that should be included in the EA
In addition to reclamation and environmental protection costs, performance securities should be required to also cover the cost of environmental damages that could occur.

The mine site should include the loss of hunting and other recreation uses. Animal Interaction with traffic and associated road kill of wildlife would increase on more roads than Maria and Toroda Creek Roads.

The EA should include a table of all of the anticipated fish and wildlife impacts and the mitigation measure that is proposed to offset that impact. The table should include short-term, long-term, and perpetual impacts. The EA fails to include a Mitigation Plan.

Water rights are an important part of the affected environment yet not mentioned in the EA. Senior water rights would be impacted by a shift in the hydrologic divide. While water rights are not generally the subject of an EA, when it is well know that a project would have significant enough impacts to change the hydrology of a mountain, impairing senior water rights and the public interest and this has been established as a ‘conclusion of law’, and the FS is analyzing the direct, indirect, and cumulative impacts of a pipeline and discharging the water onto NFS land, it should fall within the scope of the EA.

The cumulative impacts sections fail to take a hard look at foreseeable future events. It is reasonable to assume and foresee that improved access to previously inaccessible areas will result in increased development such as timber sales and mineral development. Again, the PCHB, weighed in on this one, stating in its decision at issue #14 “Ecology never considered the cumulative impacts of BMG’s new water rights and existing and future demand from exempt wells and reasonable foreseeable development projects, either independent of or prompted by the mine’s development.” A reasonable assessment of future development should be part of the EA. Drought conditions should also be considered.

The EA fails to adequately consider the potential impacts of hazardous materials in the various locations and road conditions, potentially impacting bodies of water, fish and wildlife. These concerns should be addressed more accurately in the EA.

The EA fails to consider the impacts of the mitigation itself. Mitigation plays a pivotal roll in this proposal and should be fully included as a focus of the EA.

The EA should analyzes and compare whether reducing the width of the road proposed for Marias Creek would minimizing transportation impacts of the project.

The EA cannot be considered complete because it does not contain a reclamation plan for the Buckhorn Mine itself, and there is no corresponding estimate of the reclamation costs, post-closure monitoring, maintenance, and water treatment plant operating costs, and no analysis of whether the mine operator can meet the terms of the financial surety that would be required.

A geochemical analysis of the rock in the proposed gravel pit should be done to fully understand what the impacts of building and reconstructing the Marias Creek Road would have on water quality and fish habitat. In addition, the gravel pit is purported to be infested with noxious weeds. The impact of using noxious weed infested gravel should be fully analyzed and alternatives to minimize, reduce or mitigate the impacts should be proposed.

The EA should clearly state how much water would be dewatered from the mountain. This information is needed because all of this water, except what would be consumed would be pumped to NFS land. In addition, how the water that would be pumped out of the mountain would be treated for nitrates and other contaminants before it would be pumped to an infiltration gallery or to replenish depleted stream flows should be fully analyzed since it is integral to assuring what the impacts from the infiltration gallery would be. This is all part of the mining process that the FS cannot ignore in the analysis if the related activities.

What mechanism would be used to insure that supplies and employee would use the routes described in the EA?

The EA should require that only seeds from native plants be used in all plantings.

The DSEIS for the proposed mine predicts it would take 25 to 60 or more years for the water table on Buckhorn Mountain to reach equilibrium. Many times water quality problems don’t start for 60 years. Post-closure monitoring would be critical in maintaining water quantity and quality mitigation and it should be expected to be maintained for at least 60 or more years. The EA should be fixed fully reflect this time frame..
An environmental monitoring plan, including wildlife and aquatic resources mitigation monitoring should be developed. In addition, the responsible parties for collecting, evaluation and distribution of data should be identified.

The EA should consider the traffic, noise, dust and visual quality changes could discourage on current residents future residential or other low-intensity uses along the proposed Marias Creek haul route. This the EA fails to acknowledge the impacts to community economic development efforts highlighting the scenic beauty and recreation opportunities of the areas rural character for tourism that allowing 5 to 7 trucks a minute to use Marias Creek Rd. The indirect effects of this proposal on land use was expressed as a large concern by many of the people who would be most impacted by this proposal. The EA should address these concerns not simply mention them.

The EA should look at the cumulative impacts that other or additional exploration could be developed using the access road. The EA fails to consider the 189 mining claims that the proponent has in the area. The public has a right to know the possible impacts of foreseeable future projects that could affect NFS land in the area that the EA fail on this account.

Ore trucks should be covered to reduce rocks and dust.

The EA anticipates increases of noise to be right up to the limits allowed by state law. However, the noise document states that baseline ambient sound levels INCLUDE the traffic from the K2 mine (although that mine has been closed for months). These “ambient sounds” of K2 mine traffic, when taken out of the equation, would make the increased sound of traffic on and off the proposed mine site a “very serious impact” to the quality of life in the community. The truck noise from K2 should not be considered in the baseline and landowners need to be justly compensated for these noise impacts.

An independent, local citizens group should monitor noise and be empowered to enforce noise limits in their community. These actions could include requiring heavy-duty brake mufflers, further limiting of the hours of operation, and monetary compensation to mitigate impacts landowners seriously impacted by noise.

Who’s job would it be to monitor noise impacts to Mule deer? With so many ore hauling truck, with trailer, on the haul road all the time year passing through mule deer winter range who would determine if engine-braking noise is determined to be a problem. What would be the extent of impact to mule deer? Is there is a study proposed to attempt to determine the impact? The use of specialized mufflers could reduce the impact on the mule deer. Specialized mufflers be required on all of the haul trucks.

Soils (page 101) This section fails to consider the impacts of significant rain and rain on snow events that occur commonly in this area and could cause erosion and exacerbate mine pollution. The impact of large rain events and rain on snow should be included. Erosion of cut-and-fill slopes should be addressed. The EA should include other sediment control structure, like sediment settling areas, that would increase stream protection from sediment and polluted road runoff through culverts more than riprap. How is the stability of the Toroda and Kettle River roads to be maintained considering the addition of 100 large ore truck per day over 7.5 years.Vegetation (page 298) We are concerned that the riparian vegetation will be impacted by haul route traffic and de-watering caused by changes in the road prism (widening). There are several rare plants, such as the northern bog orchid and moonwart, and says there would be no impact if best management practices (BMP’s) were implemented. We do not find in the report what the likelihood of the BMP’s being implemented and maintained are. Past projects have never had 100% effectiveness and this is unlikely to break that precedent, so we would like to see an assessment of how effective the BMP’s will be over time and how that will be monitored and funded. Dust is mentioned as impacting plant photosynthesis, and weeds are mentioned as moving into disturbed sites, but the EA fails to quantify or even estimate the actual impacts, stating they would be small. This is not rigorous science and we ask that the impacts of dust and weeds be quantified, or that the comment that the impacts would be “small” be backed up with analysis and research.
This area is part of the former North Half of the Colville Reservation and cultural plants were important and their distribution and abundance ensured by treaty rights. The EA inadequately addresses the impacts on cultural plants, fails to inventory the plants, and does not discuss whether there has been communication with the Colville Confederated Tribe about plants on site and along the haul routes.

The mitigation measures do not address the likelihood that weeds will invade newly disturbed sites and what the action will be when noxious weeds occupy those sites. A mitigation measure to require immediate restoration of disturbed sites with native plants should be included in the EA. The 61.5 acres of cleared area along the Marias Creek Road is an irreversible loss of riparian and upland habitat, which is mentioned in the DSEIS. The consequences on species viability is not measured or discussed in the EA. It is also not discussed what would happen at the end of the project with this road. We recommend it become a one-way haul road, without widening and that non-toxic dust abatement be used throughout the life of the project. Increasing noxious weeds on another 61.5 acres should be compensated for by weed elimination on similar habitat elsewhere and plans to eventually restore these 61.5 acres after the hauling is done should be part of the SEIS and Decision.Transportation (page 90) The EA fails to address spills, spill prevention and spills into aquatic resources and accidents. The DSEIS in Table S-2 on page S-12 (Summary of Environmental Impacts), No Action; “There are existing material spills that occur periodically on the highway. These spills would continue.” Then in the Proposed Action column, “Similar accident as No Action Alternative.”


Wildlife (page 203) This section tiers to two other documents, the Crown Jewel FEIS and the Kettle River Project FEIS. In the case of the Kettle River FEIS, the document was written pre-1988, and is therefore out of date, although perhaps useful as a background source of information.

Threatened, Endangered, and Candidate Species; This table lists several species and a likelihood of occurrence in the affected areas, citing the 1997 FEIS. However the project scope has changed, and this will now be an underground mine, and the ore will be hauled to the Republic mill site. In effect the mining site is smaller and more enclosed, but the affected area from hauling and motorized activity has expanded exponentially. This is a changed circumstance that requires a new look at the interactions of this project with wildlife, and new consultation with federal agencies.

The North American Lynx is now listed as a threatened species and suitable and possible occupied habitat exists near the area, and along the travel corridor, which is very close to the Jackson Roadless Area. Lynx are known to be moving into areas near Republic and are also known to travel over long distances. The SEIS fails to acknowledge any impacts on lynx within the mine site and travel route and we do not see evidence that US Fish and Wildlife has been recently consulted regarding lynx.

Wolverine have been seen in this part of Washington, in fact a wolverine was killed several years ago within a few miles of the mine site and haul route. They are also reclusive animals that could be impacted by vehicle collisions, noise such as blasting and vehicles, and access by the increased population of miners in the area. No mention was made in the wildlife section about the cumulative impacts of the increased population that would likely include hunters and motorized recreationists.

Gray wolves are returning to their once occupied habitat in Idaho and Montana and have been reported in eastern Washington as dispersal animals. Road kills or injuries can attract predators such as wolf, bald eagle, golden eagle and wolverine and the constant truck traffic and expected mortalities could impact these species. This is not discussed (except for deer) in the wildlife report.

California bighorn sheep occupy Vulcan Mountain within a half-mile of the haul route and may be expanding into the Toroda/Marias creek area. There should be consultation with Washington Department of Fish and Wildlife to assess the impacts of haul traffic on sheep populations.

Bald Eagles occupy many stretches of the haul route, are an endangered species, and yet are not discussed in the report. Consultation with US Fish and Wildlife Service should occur and mitigation impacts should be part of the SEIS. One such mitigation measure might be to lower speed limits along the Kettle River and Curlew Creek part of the haul route.

Impacts of the hauling along Marias Creek, Toroda Creek, the Kettle River, and Curlew Creek are not addressed with regards to impacts on riparian vegetation and wildlife. Noise, dust, herbicides to restrict noxious weeds are all issues of importance along roads. When those roads are within riparian areas the concerns are increased. Since some of the water bodies near the mine site will be de-watered, it may cause birds and mammals to be displaced to other riparian areas.

The EA underestimates the impacts to mule deer and other wildlife. noise from construction and operation of the haul road could affect some species substantially more than an amount equal to doubling the width of the road as indicated by the Forman, 2000. A substantially greater amount of mitigation should be required for this.